09. 05. 2023

ELTRA, s.r.o. – Main contractor

Realization: 05/2023 - still working

Brief description:

The subject of the contract is the electrification of the existing single-track railway line with a one-way traction system of 3 kV and the implementation of the related reconstruction of the facilities and constructions of the railway infrastructure on the section of the Bánovce nad Ondavou – Humenné line in a length of 33.5 km.

The implementation of the related reconstruction mainly represents pre-electrification modifications, construction of category 3 security devices, reconstruction and modification of equipment and structures of the railway top and bottom, as well as other required works according to the project documentation provided by the contracting authority (for two parts of the work) and according to the project documentation required to be prepared and delivered within this order (for one part of the work).

The work consists of 3 parts of the work (3 constructions) as follows:

  1. Building A "ŽST Bánovce nad Ondavou (outside) - ŽST Strážske (including), KRŽZ, col. no. 1"
  2. Building B "ŽST Michalovce - station security equipment"
  3. Building C "ŽSR, Electrification of the Bánovce nad Ondavou – Humenné line"